We have not checked Knowlton's own rules yet. New Jersey (NJ) guidance: A shed of 200 square feet or less and 10 feet tall or less, with no water, gas, oil or sewer hookups, does not need a building permit in NJ. If you run power to it you need an electrical permit.

3 min read

On This Page

Not Verified Yet

We have not checked Knowlton's own rules for this yet. Here is what New Jersey law says, which applies everywhere.

A shed of 200 square feet or less and 10 feet tall or less, with no water, gas, oil or sewer hookups, does not need a building permit in NJ. If you run power to it you need an electrical permit. Most towns still want a zoning permit and set back distances from property lines.

How to check with Knowlton

State rule · N.J.A.C. 5:23-2.14(b)(8)

What New Jersey law says

A shed of 200 square feet or less and 10 feet tall or less, with no water, gas, oil or sewer hookups, does not need a building permit in NJ. If you run power to it you need an electrical permit. Most towns still want a zoning permit and set back distances from property lines.

How to do it in Knowlton

General North Jersey guidance. Confirm local requirements with Knowlton.

  1. 1

    Measure the shed's footprint and height.

  2. 2

    Check Knowlton's setbacks from property lines and the house.

  3. 3

    Apply for a zoning permit if required.

  4. 4

    Get an electrical permit if you are running power to it.

  5. 5

    Set it on a level base and keep it out of easements and drainage paths.

What to bring

  • Property survey with the shed location
  • Shed dimensions and height
  • Product sheet or plans

Cost and timing

Typical cost
Zoning permits are often under $100
Typical timing
Usually 1 to 2 weeks

Typical across North Jersey. Knowlton sets its own fees.

Common mistakes

  • Placing it inside a required setback
  • Running power without an electrical permit
  • Putting it over a utility easement

Questions people ask

Who handles this in Knowlton

Construction official and zoning officer

This is the usual place to start in New Jersey. Ask Knowlton which office handles your situation.

Key terms

Setback
The minimum distance between a structure and a property line or another feature named in the zoning rules.
Zoning permit
Local approval that a use or project fits the town's land use rules.
Construction permit
Approval for work covered by the building, electrical, plumbing or other construction codes.